Cheniere Energy has successfully produced the first liquefied natural gas (LNG) at the first train of its Corpus Christi stage three liquefaction project in Texas.
The third stage of the Corpus Christi project consists of seven mid-scale trains, with an expected total production capacity of over 10 million tonnes per annum of LNG.
As of 30th November 2024, Corpus Christi stage three was just under 80% complete.
Cheniere expects substantial completion of the first train to be achieved by the end of the first quarter, over six months ahead of the guaranteed completion date.